Weekly update on Beach Access repairs from Nor’Ida

Grace,

As of this morning, 7 of the 9 Beach Accesses are substantially complete and currently being utilized by the public.

Whaler Ct. will be completed today – remaining work is debris clean up.

Sandalwood Rd.  & Great Neck Rd. Accesses – Still waiting for the railing fittings to be delivered to install the ADA handrail & non-skid strips on the ramping at Sandalwood Rd. and the steel handrail and fittings at Great Neck Rd.

Velzey Ave. – Construction to begin tomorrow and should be completed by this weekend.

Delays have been due to specialized material deliveries from manufacturers and , specifically this week, contractor equipment breakdown.

Should you have any additional questions or concerns, please contact me at your earliest convenience.

Very truly yours,

Karl L. Smithson, APM
PW/Operations - Technical Support
385-1540 (Office)
403-3821 (Cell)

Topics: Nor'Ida Shore Drive News Shore Drive Safety Issues
Posted on 06.23.2010 @ 11:20 AM by Tim. Permalink for Emails